Estimated Crew Labor Duration

Choose the crew size. The planning default is 8 hours per painter, per workday.

Crew Size
Schedule About4 working days

100 painter-hours ÷ (4 painters × 8 hours/day) = 3.13 working days

Labor-capacity estimate—not a guaranteed calendar completion date. Include setup, preparation, and cleanup in total painter-hours. Weather, drying time, access delays, sequencing, and change orders can extend calendar time.